πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Onshore Wind

Burton Wold Wind Farm Extension (Southern)

Glendon Farm (land at), Near Burton Latimer,, Northamptonshire

Burton Wold Wind Farm Extension (Southern) is a 8.6 MW onshore wind project in East Midlands. The applicant or operator on record is Infinergy. The application has been withdrawn or the scheme abandoned. The determining authority is North Northamptonshire, reference KET/2011/0506…

Withdrawn
Project stageWithdrawn / abandoned
  1. PlanningAug 2011 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedApr 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Abandoned.

Official register: July 2026

Recorded status: Abandoned. Source record updated 2016-11-18.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

8.600 MW
Registered Capacity

πŸ“‹ Project Overview

Burton Wold Wind Farm Extension (Southern) is a 8.6 MW onshore wind project in East Midlands. The applicant or operator on record is Infinergy. The application has been withdrawn or the scheme abandoned. The determining authority is North Northamptonshire, reference KET/2011/0506.

Site Schematic

EAST MIDLANDS Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)8.600 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperInfinergy
Owner / operatorInfinergy
Year consented2012
LocationGlendon Farm (land at), Near Burton Latimer,, Northamptonshire
RegionEast Midlands
Coordinates52.3502345Β°N, 0.6502461Β°W

Additional published register fields

Registered technologyWind Onshore
Turbine Capacity (MW)2.8
No. of Turbines3
Height of Turbines (m)137

πŸ“… Project Timeline

2011-08-24
2012-04-02