Burton Lane End, Burton Waters, Lincoln, Lincolnshire, LN1 2UA
Burton Lane - Micro Energy Storage is a 0.2 MW battery storage project in East Midlands. The applicant or operator on record is AMP Clean Energy. The scheme is currently in the planning system, submitted August 2024. The determining authority is West Lindsey, reference WL/2024/00β¦
Revised
Project stageSuperseded by a new application
PlanningAug 2024 (completed)
Superseded by a new application (project stopped here)
Consented (not reached)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Revised.
Official register: July 2026
Recorded status: Revised. Source record updated 2024-09-23.
Registered planning capacity; not measured generation.
Burton Lane - Micro Energy Storage is a 0.2 MW battery storage project in East Midlands. The applicant or operator on record is AMP Clean Energy. The scheme is currently in the planning system, submitted August 2024. The determining authority is West Lindsey, reference WL/2024/00667.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
0.200 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
AMP Clean Energy
Owner / operator
AMP Clean Energy
Location