Burnbank Street, Greenhill - Battery Storage Facility is a 30 MW battery storage project in Scotland. The applicant or operator on record is Renewable Connections Developments Limited. Planning permission has been granted as of August 2024 and it is awaiting construction. The det…

Consented / Approved
Project stageConsented
  1. PlanningFeb 2024 (completed)
  2. ConsentedAug 2024 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2024-09-09.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

30.000 MW
Power Capacity

πŸ“‹ Project Overview

Burnbank Street, Greenhill - Battery Storage Facility is a 30 MW battery storage project in Scotland. The applicant or operator on record is Renewable Connections Developments Limited. Planning permission has been granted as of August 2024 and it is awaiting construction. The determining authority is North Lanarkshire, reference 24/00043/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)30.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperRenewable Connections Developments Limited
Owner / operatorRenewable Connections Developments Limited
Year consented2024
LocationS/O Burnbank Street, Greenhill, Lanarkshire, ML5
RegionScotland
Coordinates55.8692206Β°N, 4.0153053Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2024-02-06