πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Battery Storage

Burbo Bank Energy Storage

Burbo Banks Electricity Sub Station, BRECK ROAD, POULTON, Merseyside, CH44 3EQ

Burbo Bank Energy Storage is a 2 MW battery storage project in North West. The applicant or operator on record is Ørsted. It is recorded as operational since December 2018. The determining authority is Wirral, reference APP/17/00463.…

Operational Β· Since 2018
Project stageOperating
  1. PlanningApr 2017 (completed)
  2. Consented (completed)
  3. ConstructionOct 2018 (completed)
  4. OperatingDec 2018 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2020-02-26.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2.000 MW
Power Capacity
2018
Commissioned

πŸ“‹ Project Overview

Burbo Bank Energy Storage is a 2 MW battery storage project in North West. The applicant or operator on record is Ørsted. It is recorded as operational since December 2018. The determining authority is Wirral, reference APP/17/00463.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)2.000 MW
Battery chemistryCo-located with RE

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperØrsted
Owner / operatorØrsted
Construction started2018
Commissioned / target2018
LocationBurbo Banks Electricity Sub Station, BRECK ROAD, POULTON, Merseyside, CH44 3EQ
RegionNorth West
Coordinates53.4123468Β°N, 3.0551116Β°W

Additional published register fields

Registered technologyBattery
Storage Co-location REPD Ref ID2487

πŸ“… Project Timeline

2017-04-14
2018-10-24
2018-12-24