Bryn Lane Wrexham, Clwyd

Bryn Lane Recycling is a 5.2 MW bioenergy / waste project in Wales. The applicant or operator on record is HLC Projects Ltd / Compact Power. The application has been withdrawn or the scheme abandoned. The determining authority is Wrexham, reference P/2005/0334.…

Withdrawn
Project stageWithdrawn / abandoned
  1. PlanningMar 2005 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Planning Application Withdrawn.

Official register: July 2026

Recorded status: Planning Application Withdrawn. Source record updated 2014-12-02.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

5.200 MW
Registered Capacity

πŸ“‹ Project Overview

Bryn Lane Recycling is a 5.2 MW bioenergy / waste project in Wales. The applicant or operator on record is HLC Projects Ltd / Compact Power. The application has been withdrawn or the scheme abandoned. The determining authority is Wrexham, reference P/2005/0334.

πŸ”§ Technical Specifications

Capacity (MW)5.200 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperHLC Projects Ltd / Compact Power
Owner / operatorHLC Projects Ltd / Compact Power
LocationBryn Lane Wrexham, Clwyd
RegionWales
Coordinates53.0437169Β°N, 2.9114383Β°W

Additional published register fields

Registered technologyEfW Incineration

πŸ“… Project Timeline

2005-03-24