Battery Storage

Broxburn

Land at Lookabootye, by Broxburn, adjacent to the Lookabootye substation., West Lothian

Broxburn is a 20 MW battery storage project in Scotland. The applicant or operator on record is Renewable Energy Systems (RES). It is recorded as operational since September 2018. The determining authority is West Lothian, reference LIVE/0502/FUL/16.…

Operational Β· Since 2018
Project stageOperating
  1. PlanningAug 2016 (completed)
  2. ConsentedNov 2016 (completed)
  3. ConstructionAug 2017 (completed)
  4. OperatingSep 2018 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2019-04-18.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

20.000 MW
Power Capacity
2018
Commissioned

πŸ“‹ Project Overview

Broxburn is a 20 MW battery storage project in Scotland. The applicant or operator on record is Renewable Energy Systems (RES). It is recorded as operational since September 2018. The determining authority is West Lothian, reference LIVE/0502/FUL/16.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)20.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperRenewable Energy Systems (RES)
Owner / operatorRenewable Energy Systems (RES)
Year consented2016
Construction started2017
Commissioned / target2018
LocationLand at Lookabootye, by Broxburn, adjacent to the Lookabootye substation., West Lothian
RegionScotland
Coordinates55.9192431Β°N, 3.4553531Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2016-08-03
2016-11-25
2017-08-15
2018-09-15