Broughall Fields Farm is a 2.4 MW bioenergy / waste project in West Midlands. The applicant or operator on record is Grocontinental/ Whitchurch Biogas. It is recorded as operational since March 2017. The determining authority is Shropshire, reference 14/01398/MAW.…

Operational Β· Since 2017
Project stageOperating
  1. PlanningMar 2014 (completed)
  2. ConsentedDec 2014 (completed)
  3. ConstructionAug 2016 (completed)
  4. OperatingMar 2017 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2018-03-28.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2.400 MW
Registered Capacity
2017
Commissioned

πŸ“‹ Project Overview

Broughall Fields Farm is a 2.4 MW bioenergy / waste project in West Midlands. The applicant or operator on record is Grocontinental/ Whitchurch Biogas. It is recorded as operational since March 2017. The determining authority is Shropshire, reference 14/01398/MAW.

πŸ”§ Technical Specifications

Capacity (MW)2.400 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperGrocontinental/ Whitchurch Biogas
Owner / operatorGrocontinental/ Whitchurch Biogas
Year consented2014
Construction started2016
Commissioned / target2017
LocationBroughall Fields Farm, Ash Road, Whitchurch,, Shropshire, SY13 4DE
RegionWest Midlands
Coordinates52.962501Β°N, 2.6624262Β°W

Additional published register fields

Registered technologyAnaerobic Digestion

πŸ“… Project Timeline

2014-03-28
2014-12-19
2016-08-01
2017-03-30