Bioenergy / Waste

Bromborough Dock Landfill Scheme

Dock Road South Bromborough Merseyside, Merseyside

Bromborough Dock Landfill Scheme is a 3 MW bioenergy / waste project in North West. The applicant or operator on record is Biffa. It is recorded as operational since September 1999. The determining authority is Wirral.…

Operational Β· Since 1999
Project stageOperating
  1. PlanningFeb 1999 (completed)
  2. ConsentedMay 1999 (completed)
  3. Construction (completed)
  4. OperatingSep 1999 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2004-12-09.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

3.000 MW
Registered Capacity
1999
Commissioned

πŸ“‹ Project Overview

Bromborough Dock Landfill Scheme is a 3 MW bioenergy / waste project in North West. The applicant or operator on record is Biffa. It is recorded as operational since September 1999. The determining authority is Wirral.

πŸ”§ Technical Specifications

Capacity (MW)3.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperBiffa
Owner / operatorBiffa
Year consented1999
Commissioned / target1999
LocationDock Road South Bromborough Merseyside, Merseyside
RegionNorth West
Coordinates53.3560545Β°N, 2.9795572Β°W

Additional published register fields

Registered technologyLandfill Gas

πŸ“… Project Timeline

1999-02-10
1999-05-21
1999-09-29