Land At Broadditch Farm New Barn Road Southfleet, Kent, DA13 9PU
Broadditch Battery Energy is a 11 MW battery storage project in South East. The applicant or operator on record is Harmony Energy. It is recorded as operational since March 2023. The determining authority is Dartford, reference 18/00637/FUL.β¦
OperationalΒ· Since 2023
Project stageOperating
PlanningMay 2018 (completed)
ConsentedAug 2018 (completed)
Construction (completed)
OperatingMar 2023 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2026-02-02.
Registered planning capacity; not measured generation.
Broadditch Battery Energy is a 11 MW battery storage project in South East. The applicant or operator on record is Harmony Energy. It is recorded as operational since March 2023. The determining authority is Dartford, reference 18/00637/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
11.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Harmony Energy
Owner / operator
Harmony Energy
Year consented
2018
Commissioned / target
2023
Location
Land At Broadditch Farm New Barn Road Southfleet, Kent, DA13 9PU