Bioenergy / Waste

Briton / Neath

Neath Landfill, Giant Grave Road, West Glamorgan, West Glamorgan

Briton / Neath is a 2.2 MW bioenergy / waste project in Wales. The applicant or operator on record is Natural Power. It is recorded as operational since June 2004. The determining authority is Neath Port Talbot.…

Operational Β· Since 2004
Project stageOperating
  1. PlanningApr 2000 (completed)
  2. ConsentedJun 2000 (completed)
  3. Construction (completed)
  4. OperatingJun 2004 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2009-07-15.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2.200 MW
Registered Capacity
2004
Commissioned

πŸ“‹ Project Overview

Briton / Neath is a 2.2 MW bioenergy / waste project in Wales. The applicant or operator on record is Natural Power. It is recorded as operational since June 2004. The determining authority is Neath Port Talbot.

πŸ”§ Technical Specifications

Capacity (MW)2.200 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperNatural Power
Owner / operatorNatural Power
Year consented2000
Commissioned / target2004
LocationNeath Landfill, Giant Grave Road, West Glamorgan, West Glamorgan
RegionWales
Coordinates51.6430841Β°N, 3.8324677Β°W

Additional published register fields

Registered technologyLandfill Gas

πŸ“… Project Timeline

2000-04-26
2000-06-06