Briton Ferry is a 2 MW bioenergy / waste project in Wales. The applicant or operator on record is Neath Port Talbot Waste Management Co Ltd. It is recorded as operational since September 2004. The determining authority is Neath Port Talbot, reference 961021.…

Operational Β· Since 2004
Project stageOperating
  1. PlanningApr 1996 (completed)
  2. ConsentedJun 1996 (completed)
  3. Construction (completed)
  4. OperatingSep 2004 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2004-10-04.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2.000 MW
Registered Capacity
2004
Commissioned

πŸ“‹ Project Overview

Briton Ferry is a 2 MW bioenergy / waste project in Wales. The applicant or operator on record is Neath Port Talbot Waste Management Co Ltd. It is recorded as operational since September 2004. The determining authority is Neath Port Talbot, reference 961021.

πŸ”§ Technical Specifications

Capacity (MW)2.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperNeath Port Talbot Waste Management Co Ltd
Owner / operatorNeath Port Talbot Waste Management Co Ltd
Year consented1996
Commissioned / target2004
LocationGiants Grave Road, Briton Ferry, Neath,, West Glamorgan
RegionWales
Coordinates51.642208Β°N, 3.8309871Β°W

Additional published register fields

Registered technologyLandfill Gas

πŸ“… Project Timeline

1996-04-18
1996-06-05
2004-09-01