Land at Brickyard Barn, Mallory Road, Bishops Tachbrook, Leamington Spa, Warwickshire, CV33 9QD
Brickyard Barn is a 4.1 MW solar farm project in West Midlands. The applicant or operator on record is Sun Glow Power. It is recorded as operational since November 2014. The determining authority is Warwick, reference W/13/1608.β¦
OperationalΒ· Since 2014
Project stageOperating
PlanningNov 2013 (completed)
ConsentedDec 2013 (completed)
ConstructionOct 2014 (completed)
OperatingNov 2014 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2014-11-27.
Registered planning capacity; not measured generation.
Brickyard Barn is a 4.1 MW solar farm project in West Midlands. The applicant or operator on record is Sun Glow Power. It is recorded as operational since November 2014. The determining authority is Warwick, reference W/13/1608.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
4.100 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Sun Glow Power
Owner / operator
Sun Glow Power
Year consented
2013
Construction started
2014
Commissioned / target
2014
Location
Land at Brickyard Barn, Mallory Road, Bishops Tachbrook, Leamington Spa, Warwickshire, CV33 9QD