Boxted Airfield is a 18.8 MW solar farm project in Eastern. The applicant or operator on record is NextEnergy Solar Fund. It is recorded as operational since March 2015. The determining authority is Colchester, reference 145101.β¦
OperationalΒ· Since 2015
Project stageOperating
PlanningJun 2014 (completed)
ConsentedSep 2014 (completed)
ConstructionNov 2014 (completed)
OperatingMar 2015 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2015-08-14.
Registered planning capacity; not measured generation.
Boxted Airfield is a 18.8 MW solar farm project in Eastern. The applicant or operator on record is NextEnergy Solar Fund. It is recorded as operational since March 2015. The determining authority is Colchester, reference 145101.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.