πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Onshore Wind

Boulfruich

Houstry Dunbeath Caithness, Highland

Boulfruich is a 13 MW onshore wind project in Scotland. The applicant or operator on record is Private Developer. It is recorded as operational since August 2005. The determining authority is Highland, reference CA2001306.…

Operational Β· Since 2005
Project stageOperating
  1. PlanningSep 2001 (completed)
  2. ConsentedMay 2002 (completed)
  3. Construction (completed)
  4. OperatingAug 2005 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2009-10-23.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

13.000 MW
Registered Capacity
2005
Commissioned

πŸ“‹ Project Overview

Boulfruich is a 13 MW onshore wind project in Scotland. The applicant or operator on record is Private Developer. It is recorded as operational since August 2005. The determining authority is Highland, reference CA2001306.

Site Schematic

SCOTLAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)13.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperPrivate Developer
Owner / operatorPrivate Developer
Year consented2002
Commissioned / target2005
LocationHoustry Dunbeath Caithness, Highland
RegionScotland
Coordinates58.2999375Β°N, 3.443354Β°W

Additional published register fields

Registered technologyWind Onshore
Turbine Capacity (MW)0.85
No. of Turbines15

πŸ“… Project Timeline

2001-09-17
2002-05-29
2005-08-01