Battery Storage

Boscar Grange Farm

Boscar Grange Farm, Thirsk Road, Easingwold, York, North Yorkshire, North Yorkshire, YO61 3NQ

Boscar Grange Farm is a 27 MW battery storage project in Yorkshire and Humber. The applicant or operator on record is Gridserve. It is recorded as operational since December 2019. The determining authority is North Yorkshire, reference 18/02314/NMC.…

Operational Β· Since 2019
Project stageOperating
  1. PlanningOct 2018 (completed)
  2. Consented (completed)
  3. ConstructionMay 2019 (completed)
  4. OperatingDec 2019 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2019-12-18.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

27.000 MW
Power Capacity
2019
Commissioned

πŸ“‹ Project Overview

Boscar Grange Farm is a 27 MW battery storage project in Yorkshire and Humber. The applicant or operator on record is Gridserve. It is recorded as operational since December 2019. The determining authority is North Yorkshire, reference 18/02314/NMC.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)27.000 MW
Battery chemistryCo-located with RE

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperGridserve
Owner / operatorGridserve
Construction started2019
Commissioned / target2019
LocationBoscar Grange Farm, Thirsk Road, Easingwold, York, North Yorkshire, North Yorkshire, YO61 3NQ
RegionYorkshire and Humber
Coordinates54.1444602Β°N, 1.2281011Β°W

Additional published register fields

Registered technologyBattery
Storage Co-location REPD Ref ID5482

πŸ“… Project Timeline

2018-10-29
2019-05-23
2019-12-18