Land off Bob Lane, North Lodge, Twineham, Haywards Heath, West Sussex, RH17 5NH
Bolney Substation - Battery Storage is a 264 MW battery storage project in South East. The applicant or operator on record is One Planet Developments Limited. Planning permission has been granted as of October 2024 and it is awaiting construction. The determining authority is Midβ¦
Consented / Approved
Project stageConsented
PlanningMar 2023 (completed)
ConsentedOct 2024 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2024-10-28.
Registered planning capacity; not measured generation.
Bolney Substation - Battery Storage is a 264 MW battery storage project in South East. The applicant or operator on record is One Planet Developments Limited. Planning permission has been granted as of October 2024 and it is awaiting construction. The determining authority is Mid Sussex, reference DM/23/0769.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
264.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
One Planet Developments Limited
Owner / operator
One Planet Developments Limited
Year consented
2024
Location