UNIT 5, BLOXWICH LANE INDUSTRIAL ESTATE, BLOXWICH LANE, WALSALL, WS2 8TF, West Midlands, WS2 8TF
Bloxwich Battery is a 41 MW battery storage project in West Midlands. The applicant or operator on record is Gresham House Energy Storage. It is recorded as operational since July 2019. The determining authority is Walsall, reference 16/1536.β¦
OperationalΒ· Since 2019
Project stageOperating
PlanningSep 2016 (completed)
ConsentedFeb 2022 (completed)
Construction (completed)
OperatingJul 2019 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2020-09-30.
Registered planning capacity; not measured generation.
Bloxwich Battery is a 41 MW battery storage project in West Midlands. The applicant or operator on record is Gresham House Energy Storage. It is recorded as operational since July 2019. The determining authority is Walsall, reference 16/1536.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
41.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Gresham House Energy Storage
Owner / operator
Gresham House Energy Storage
Year consented
2022
Commissioned / target
2019
Location
UNIT 5, BLOXWICH LANE INDUSTRIAL ESTATE, BLOXWICH LANE, WALSALL, WS2 8TF, West Midlands, WS2 8TF