7km north west of Inveraray and 6km east of Dalavich, Argyll and Bute

Blarghour Wind Farm is a 84 MW onshore wind project in Scotland. The applicant or operator on record is Coriolis Energy / ESB. Planning permission has been granted as of October 2021 and it is awaiting construction. The determining authority is Scottish Government (S36), referenc…

Consented / Approved
Project stageConsented
  1. PlanningMay 2018 (completed)
  2. ConsentedOct 2021 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2024-10-07.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

84.000 MW
Registered Capacity

πŸ“‹ Project Overview

Blarghour Wind Farm is a 84 MW onshore wind project in Scotland. The applicant or operator on record is Coriolis Energy / ESB. Planning permission has been granted as of October 2021 and it is awaiting construction. The determining authority is Scottish Government (S36), reference EC00005267.

Site Schematic

SCOTLAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)84.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperCoriolis Energy / ESB
Owner / operatorCoriolis Energy / ESB
Year consented2021
Location7km north west of Inveraray and 6km east of Dalavich, Argyll and Bute
RegionScotland
Coordinates56.2717621Β°N, 5.1715633Β°W

Additional published register fields

Registered technologyWind Onshore
CfD Allocation RoundAR5
CfD Capacity (MW)67.2
Turbine Capacity (MW)6.6
No. of Turbines14
Height of Turbines (m)180

πŸ“… Project Timeline

2018-05-14