Blantyre Muir Wind Farm extension is a 7.5 MW onshore wind project in Scotland. The applicant or operator on record is West Coast Energy. It is recorded as operational since January 2014. The determining authority is South Lanarkshire, reference HM/10/0478.…

Operational Β· Since 2014
Project stageOperating
  1. PlanningOct 2010 (completed)
  2. ConsentedMay 2012 (completed)
  3. ConstructionJun 2012 (completed)
  4. OperatingJan 2014 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2015-01-05.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

7.500 MW
Registered Capacity
2014
Commissioned

πŸ“‹ Project Overview

Blantyre Muir Wind Farm extension is a 7.5 MW onshore wind project in Scotland. The applicant or operator on record is West Coast Energy. It is recorded as operational since January 2014. The determining authority is South Lanarkshire, reference HM/10/0478.

Site Schematic

SCOTLAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)7.500 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperWest Coast Energy
Owner / operatorWest Coast Energy
Year consented2012
Construction started2012
Commissioned / target2014
LocationNear Laigh Muirhouses Farm Muttonhole Road Hamilton, Strathclyde
RegionScotland
Coordinates55.7416059Β°N, 4.0900006Β°W

Additional published register fields

Registered technologyWind Onshore
Turbine Capacity (MW)2.5
No. of Turbines3

πŸ“… Project Timeline

2010-10-04
2012-05-25
2012-06-04
2014-01-15