πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Onshore Wind

Blairadam Wind Farm

Blairadam Forest, Dunfermline, Fife

Blairadam Wind Farm is a 22.6 MW onshore wind project in Scotland. The applicant or operator on record is Partnerships for Renewables Development Company Limited. The planning application was refused. The determining authority is Fife, reference 14/00008/EIA.…

Refused
Project stageRefused
  1. PlanningJan 2014 (completed)
  2. Refused (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Planning Permission Refused.

Official register: July 2026

Recorded status: Planning Permission Refused. Source record updated 2016-11-01.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

22.600 MW
Registered Capacity

πŸ“‹ Project Overview

Blairadam Wind Farm is a 22.6 MW onshore wind project in Scotland. The applicant or operator on record is Partnerships for Renewables Development Company Limited. The planning application was refused. The determining authority is Fife, reference 14/00008/EIA.

Site Schematic

SCOTLAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)22.600 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperPartnerships for Renewables Development Company Limited
Owner / operatorPartnerships for Renewables Development Company Limited
LocationBlairadam Forest, Dunfermline, Fife
RegionScotland
Coordinates56.1349047Β°N, 3.4641192Β°W

Additional published register fields

Registered technologyWind Onshore
Turbine Capacity (MW)2.05
No. of Turbines11

πŸ“… Project Timeline

2014-01-24