Battery Storage

Blackpark House - Battery Storage

South Of Blackpark House Nairn, Highland, IV12 5HY

Blackpark House - Battery Storage is a 30 MW battery storage project in Scotland. The applicant or operator on record is Anesco. Planning permission has been granted as of October 2025 and it is awaiting construction. The determining authority is Highland, reference 24/05019/FUL…

Consented / Approved
Project stageConsented
  1. PlanningDec 2024 (completed)
  2. ConsentedOct 2025 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2025-12-09.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

30.000 MW
Power Capacity

πŸ“‹ Project Overview

Blackpark House - Battery Storage is a 30 MW battery storage project in Scotland. The applicant or operator on record is Anesco. Planning permission has been granted as of October 2025 and it is awaiting construction. The determining authority is Highland, reference 24/05019/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)30.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperAnesco
Owner / operatorAnesco
Year consented2025
LocationSouth Of Blackpark House Nairn, Highland, IV12 5HY
RegionScotland
Coordinates57.5662961Β°N, 3.8144378Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2024-12-16