Blackburn Meadows in Sheffield, South Yorkshire, South Yorkshire, S9 1HF

Blackburn Meadows is a 10 MW battery storage project in Yorkshire and Humber. The applicant or operator on record is E.ON UK. It is recorded as operational since October 2017. The determining authority is Sheffield.…

Operational Β· Since 2017
Project stageOperating
  1. PlanningAug 2011 (completed)
  2. Consented (completed)
  3. ConstructionApr 2017 (completed)
  4. OperatingOct 2017 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2019-03-21.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

10.000 MW
Power Capacity
2017
Commissioned

πŸ“‹ Project Overview

Blackburn Meadows is a 10 MW battery storage project in Yorkshire and Humber. The applicant or operator on record is E.ON UK. It is recorded as operational since October 2017. The determining authority is Sheffield.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)10.000 MW
Battery chemistryCo-located with RE

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperE.ON UK
Owner / operatorE.ON UK
Construction started2017
Commissioned / target2017
LocationBlackburn Meadows in Sheffield, South Yorkshire, South Yorkshire, S9 1HF
RegionYorkshire and Humber
Coordinates53.4201346Β°N, 1.3984598Β°W

Additional published register fields

Registered technologyBattery
Storage Co-location REPD Ref ID166

πŸ“… Project Timeline

2011-08-19
2017-04-07
2017-10-09