Reach Drove, at Black Bush Farm, Whittlesey, Cambridgeshire, Cambridgeshire
Black Bush Farm is a 2.7 MW solar farm project in Eastern. The applicant or operator on record is Lark Energy. It is recorded as operational since July 2014. The determining authority is Fenland, reference F/YR11/0256/F.β¦
OperationalΒ· Since 2014
Project stageOperating
PlanningMar 2011 (completed)
ConsentedMar 2012 (completed)
ConstructionMay 2014 (completed)
OperatingJul 2014 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2014-11-28.
Registered planning capacity; not measured generation.
Black Bush Farm is a 2.7 MW solar farm project in Eastern. The applicant or operator on record is Lark Energy. It is recorded as operational since July 2014. The determining authority is Fenland, reference F/YR11/0256/F.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
2.700 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Lark Energy
Owner / operator
Lark Energy
Year consented
2012
Construction started
2014
Commissioned / target
2014
Location
Reach Drove, at Black Bush Farm, Whittlesey, Cambridgeshire, Cambridgeshire