Billingham Chemical Works is a 12 MW bioenergy / waste project in North East. The applicant or operator on record is O2N Energy (Billingham) LLP. It is recorded as operational since December 2013. The determining authority is Stockton-on-Tees, reference 10/1464/EIS.…

Operational Β· Since 2013
Project stageOperating
  1. PlanningJun 2010 (completed)
  2. ConsentedSep 2010 (completed)
  3. ConstructionMay 2011 (completed)
  4. OperatingDec 2013 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2020-01-22.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

12.000 MW
Registered Capacity
2013
Commissioned

πŸ“‹ Project Overview

Billingham Chemical Works is a 12 MW bioenergy / waste project in North East. The applicant or operator on record is O2N Energy (Billingham) LLP. It is recorded as operational since December 2013. The determining authority is Stockton-on-Tees, reference 10/1464/EIS.

πŸ”§ Technical Specifications

Capacity (MW)12.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperO2N Energy (Billingham) LLP
Owner / operatorO2N Energy (Billingham) LLP
Year consented2010
Construction started2011
Commissioned / target2013
LocationBillingham Chemical Works, Haverton Hill Road, Billingham, Teesside, County Durham
RegionNorth East
Coordinates54.5910125Β°N, 1.2741736Β°W

Additional published register fields

Registered technologyEfW Incineration

πŸ“… Project Timeline

2010-06-04
2010-09-03
2011-05-01
2013-12-01