Land At Bilbo Solar Farm, Moss-side, Crimond, Fraserburgh, Grampian, Aberdeenshire, AB43 8QJ

Bilbo Solar Farm Energy Storage is a 40 MW battery storage project in Scotland. The applicant or operator on record is Green Energy International. It is recorded as under construction since January 2024. The determining authority is Aberdeenshire, reference APP/2019/0296.…

Under Construction
Project stageUnder construction
  1. PlanningJun 2019 (completed)
  2. ConsentedOct 2019 (completed)
  3. ConstructionJan 2024 (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Under Construction.

Official register: July 2026

Recorded status: Under Construction. Source record updated 2025-02-03.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

40.000 MW
Power Capacity

πŸ“‹ Project Overview

Bilbo Solar Farm Energy Storage is a 40 MW battery storage project in Scotland. The applicant or operator on record is Green Energy International. It is recorded as under construction since January 2024. The determining authority is Aberdeenshire, reference APP/2019/0296.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)40.000 MW
Battery chemistryCo-located with RE

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperGreen Energy International
Owner / operatorGreen Energy International
Year consented2019
Construction started2024
LocationLand At Bilbo Solar Farm, Moss-side, Crimond, Fraserburgh, Grampian, Aberdeenshire, AB43 8QJ
RegionScotland
Coordinates57.5914391Β°N, 1.9045066Β°W

Additional published register fields

Registered technologyBattery
Storage Co-location REPD Ref ID6736

πŸ“… Project Timeline

2019-06-26
2019-10-18
2024-01-01