Biffa Waste Services, Fochriw Road - Battery Storage

Biffa Waste Services Ltd Trecatti Landfill Site Fochriw Road Pant-y-waun, Mid Glamorgan, CF48 4AB

Biffa Waste Services, Fochriw Road - Battery Storage is a 2 MW battery storage project in Wales. The applicant or operator on record is Biffa Waste Services. Planning permission has been granted as of January 2023 and it is awaiting construction. The determining authority is Caer…

Consented / Approved
Project stageConsented
  1. PlanningNov 2022 (completed)
  2. ConsentedJan 2023 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2023-01-17.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2.000 MW
Power Capacity

πŸ“‹ Project Overview

Biffa Waste Services, Fochriw Road - Battery Storage is a 2 MW battery storage project in Wales. The applicant or operator on record is Biffa Waste Services. Planning permission has been granted as of January 2023 and it is awaiting construction. The determining authority is Caerphilly, reference 22/0939/FULL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)2.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperBiffa Waste Services
Owner / operatorBiffa Waste Services
Year consented2023
LocationBiffa Waste Services Ltd Trecatti Landfill Site Fochriw Road Pant-y-waun, Mid Glamorgan, CF48 4AB
RegionWales
Coordinates51.7674573Β°N, 3.3209916Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2022-11-15