πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Bioenergy / Waste

Bidston Moss Landfill Scheme

Bidston Birkenhead Merseyside, Merseyside

Bidston Moss Landfill Scheme is a 2.3 MW bioenergy / waste project in North West. The applicant or operator on record is Bidston Methane Ltd. It is recorded as operational since January 1998. The determining authority is Wirral.…

Operational Β· Since 1998
Project stageOperating
  1. PlanningNov 1997 (completed)
  2. ConsentedDec 1997 (completed)
  3. Construction (completed)
  4. OperatingJan 1998 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2011-10-30.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2.300 MW
Registered Capacity
1998
Commissioned

πŸ“‹ Project Overview

Bidston Moss Landfill Scheme is a 2.3 MW bioenergy / waste project in North West. The applicant or operator on record is Bidston Methane Ltd. It is recorded as operational since January 1998. The determining authority is Wirral.

πŸ”§ Technical Specifications

Capacity (MW)2.300 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperBidston Methane Ltd
Owner / operatorBidston Methane Ltd
Year consented1997
Commissioned / target1998
LocationBidston Birkenhead Merseyside, Merseyside
RegionNorth West
Coordinates53.4100608Β°N, 3.0755751Β°W

Additional published register fields

Registered technologyLandfill Gas

πŸ“… Project Timeline

1997-11-03
1997-12-15
1998-01-19