Lands 100m South West of Magherakeel, 110kV Substation Shannaghy Road, Killeter, Strabane, BT81 7HB
BESS Facility Development in Killeter is a 82 MW battery storage project in Northern Ireland. The applicant or operator on record is Green Frog Power (Gort BESS) Limited. The application has been withdrawn or the scheme abandoned. The determining authority is Derry City and Strabβ¦
Withdrawn
Project stageWithdrawn / abandoned
PlanningSep 2024 (completed)
Withdrawn / abandoned (project stopped here)
Consented (not reached)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Planning Application Withdrawn.
Official register: July 2026
Recorded status: Planning Application Withdrawn. Source record updated 2025-08-05.
Registered planning capacity; not measured generation.
BESS Facility Development in Killeter is a 82 MW battery storage project in Northern Ireland. The applicant or operator on record is Green Frog Power (Gort BESS) Limited. The application has been withdrawn or the scheme abandoned. The determining authority is Derry City and Strabane, reference LA11/2024/0745/F.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
82.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Green Frog Power (Gort BESS) Limited
Owner / operator
Green Frog Power (Gort BESS) Limited
Location