Offshore Wind

Berwick Bank Offshore Wind Farm

Berwick Bank Offshore Wind Farm, E/O St Abbs Head, Coastline, Eyemouth, Offshore, TD14

Berwick Bank Offshore Wind Farm is a 4,100 MW offshore wind project in Offshore. The applicant or operator on record is Scottish Southern Energy Renewables. Planning permission has been granted as of July 2025 and it is awaiting construction. The determining authority is Marine S…

Consented / Approved
Project stageConsented
  1. PlanningDec 2022 (completed)
  2. ConsentedJul 2025 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2026-01-19.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

4,100.000 MW
Registered Capacity

πŸ“‹ Project Overview

Berwick Bank Offshore Wind Farm is a 4,100 MW offshore wind project in Offshore. The applicant or operator on record is Scottish Southern Energy Renewables. Planning permission has been granted as of July 2025 and it is awaiting construction. The determining authority is Marine Scotland, reference NA.

Site Schematic

β—„ SHORE (~? km) NORTH SEA / OFFSHORE Turbine () Export cable

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)4,100.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperScottish Southern Energy Renewables
Owner / operatorScottish Southern Energy Renewables
Year consented2025
LocationBerwick Bank Offshore Wind Farm, E/O St Abbs Head, Coastline, Eyemouth, Offshore, TD14
RegionOffshore
Coordinates56.443139Β°N, 1.466402Β°W

Additional published register fields

Registered technologyWind Offshore
CfD Allocation RoundAR7
CfD Capacity (MW)1380
Turbine Capacity (MW)13.3
No. of Turbines307
Height of Turbines (m)200

πŸ“… Project Timeline

2022-12-09
2025-07-31