Beltonanean 2 is a 2.3 MW onshore wind project in Northern Ireland. The applicant or operator on record is Private Developer. The planning permission has expired. The determining authority is Mid Ulster, reference LA09/2017/0272/F.…

Expired
Project stageConsent lapsed
  1. PlanningMar 2017 (completed)
  2. ConsentedMay 2022 (completed)
  3. Consent lapsed (project stopped here)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Planning Permission Expired.

Official register: July 2026

Recorded status: Planning Permission Expired. Source record updated 2019-05-16.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2.300 MW
Registered Capacity

πŸ“‹ Project Overview

Beltonanean 2 is a 2.3 MW onshore wind project in Northern Ireland. The applicant or operator on record is Private Developer. The planning permission has expired. The determining authority is Mid Ulster, reference LA09/2017/0272/F.

Site Schematic

NORTHERN IRELAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)2.300 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperPrivate Developer
Owner / operatorPrivate Developer
Year consented2022
LocationBeltonanean Mountain, Beltonanean TD, Cookstown,, Co. Tyrone, BT80 0A
RegionNorthern Ireland
Coordinates54.6856711Β°N, 6.8876226Β°W

Additional published register fields

Registered technologyWind Onshore
Turbine Capacity (MW)2.3
No. of Turbines1
Height of Turbines (m)93
Are they re-applying (Old REPD Ref) 5087

πŸ“… Project Timeline

2017-03-02
2022-05-30