πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Bioenergy / Waste

Beddingham 'B' Landfill Scheme

Beddingham Landfill Site Old Rodwell Cement Works Beddingham East Sussex, East Sussex

Beddingham 'B' Landfill Scheme is a 7.5 MW bioenergy / waste project in South East. The applicant or operator on record is Haul Waste Disposal Ltd. It is recorded as operational since May 1998. The determining authority is Lewes.…

Operational Β· Since 1998
Project stageOperating
  1. PlanningMar 1997 (completed)
  2. ConsentedJun 1997 (completed)
  3. Construction (completed)
  4. OperatingMay 1998 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2009-12-10.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

7.500 MW
Registered Capacity
1998
Commissioned

πŸ“‹ Project Overview

Beddingham 'B' Landfill Scheme is a 7.5 MW bioenergy / waste project in South East. The applicant or operator on record is Haul Waste Disposal Ltd. It is recorded as operational since May 1998. The determining authority is Lewes.

πŸ”§ Technical Specifications

Capacity (MW)7.500 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperHaul Waste Disposal Ltd
Owner / operatorHaul Waste Disposal Ltd
Year consented1997
Commissioned / target1998
LocationBeddingham Landfill Site Old Rodwell Cement Works Beddingham East Sussex, East Sussex
RegionSouth East
Coordinates50.8489794Β°N, 0.0512997Β°E

Additional published register fields

Registered technologyLandfill Gas

πŸ“… Project Timeline

1997-03-24
1997-06-23
1998-05-18