π Project Overview
Battery Energy Storage System Facility in Antrim is a 50 MW battery storage project in Northern Ireland. The applicant or operator on record is Heron Storage Limited. Planning permission has been granted as of March 2025 and it is awaiting construction. The determining authority is Antrim and Newtownabbey, reference LA03/2024/0351/F.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
| Capacity (MW) | 50 MW |
| Battery chemistry | Stand-alone Storage |
π Grid Connection & Infrastructure
π’ Development & Ownership
| Developer | Heron Storage Limited |
| Owner / operator | Heron Storage Limited |
| Year consented | 2025 |
| Location | Lands Approximately 550m S. of 99 Dublin Rd. and , 650m W. of 120 Dublin Road, Antrim, Newtownabbey, BT41 4SA |
| Region | Northern Ireland |
| Coordinates | 54.6833924Β°N, 6.2240952Β°W |