Land adjacent Highfield Farm, Bassingbourn, Cambridge, Cambridgeshire
Bassingbourn Solar Farm is a 14.4 MW solar farm project in Eastern. The applicant or operator on record is Push Energy. It is recorded as operational since March 2015. The determining authority is South Cambridgeshire, reference S/0098/14/FL.β¦
OperationalΒ· Since 2015
Project stageOperating
PlanningJan 2014 (completed)
ConsentedAug 2014 (completed)
ConstructionOct 2014 (completed)
OperatingMar 2015 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2015-04-28.
Registered planning capacity; not measured generation.
Bassingbourn Solar Farm is a 14.4 MW solar farm project in Eastern. The applicant or operator on record is Push Energy. It is recorded as operational since March 2015. The determining authority is South Cambridgeshire, reference S/0098/14/FL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
14.400 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Push Energy
Owner / operator
Push Energy
Year consented
2014
Construction started
2014
Commissioned / target
2015
Location
Land adjacent Highfield Farm, Bassingbourn, Cambridge, Cambridgeshire