Basing Road is a 20 MW battery storage project in South East. The applicant or operator on record is Eco-Economix. The scheme is currently in the planning system, submitted July 2021. The determining authority is Basingstoke and Deane, reference 21/02412/FUL.…

In Planning
Project stageIn planning
  1. PlanningJul 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Application Submitted.

Official register: July 2026

Recorded status: Planning Application Submitted. Source record updated 2023-02-24.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

20.000 MW
Power Capacity

πŸ“‹ Project Overview

Basing Road is a 20 MW battery storage project in South East. The applicant or operator on record is Eco-Economix. The scheme is currently in the planning system, submitted July 2021. The determining authority is Basingstoke and Deane, reference 21/02412/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)20.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperEco-Economix
Owner / operatorEco-Economix
LocationLand At, Basing Road, Old Basing, Basingstoke,, Hampshire, RG24 7AL
RegionSouth East
Coordinates51.2688127Β°N, 1.0620839Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2021-07-20