Bascote Road Solar Farm is a 4.6 MW solar farm project in West Midlands. The applicant or operator on record is TGC Renewables. The planning permission has expired. The determining authority is Stratford-on-Avon, reference 15/01740/FUL.…

Expired
Project stageConsent lapsed
  1. PlanningJun 2015 (completed)
  2. ConsentedSep 2016 (completed)
  3. Consent lapsed (project stopped here)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Planning Permission Expired.

Official register: July 2026

Recorded status: Planning Permission Expired. Source record updated 2019-12-04.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

4.600 MW
Registered Capacity

πŸ“‹ Project Overview

Bascote Road Solar Farm is a 4.6 MW solar farm project in West Midlands. The applicant or operator on record is TGC Renewables. The planning permission has expired. The determining authority is Stratford-on-Avon, reference 15/01740/FUL.

Site Schematic

SUBSTATION ? ha Β· 4.6 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)4.600 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperTGC Renewables
Owner / operatorTGC Renewables
Year consented2016
LocationBallysallagh Road and Clandeboye Avenue, Bascote, Warwickshire, CV47 9NN
RegionWest Midlands
Coordinates52.2829024Β°N, 1.3995768Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Solar Site Area (sqm)80000

πŸ“… Project Timeline

2015-06-03
2016-09-05