Land 3370M West Of Ardantiobai, Morvern, Acharacle, Strathclyde, Highland, PH36 4JA
Barr River, Loch Teacuis is a 1.7 MW conventional hydro project in Scotland. The applicant or operator on record is Morvern Community. It is recorded as operational since July 2021. The determining authority is Highland, reference 18/04708/FUL.β¦
OperationalΒ· Since 2021
Official register: July 2026
Recorded status: Operational. Source record updated 2021-11-23.
Registered planning capacity; not measured generation.
Barr River, Loch Teacuis is a 1.7 MW conventional hydro project in Scotland. The applicant or operator on record is Morvern Community. It is recorded as operational since July 2021. The determining authority is Highland, reference 18/04708/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
1.700 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Morvern Community
Owner / operator
Morvern Community
Year consented
2021
Construction started
2020
Commissioned / target
2021
Location
Land 3370M West Of Ardantiobai, Morvern, Acharacle, Strathclyde, Highland, PH36 4JA