Barnsley Battery Energy Storage is a 40 MW battery storage project in Yorkshire and Humber. The applicant or operator on record is G2 Energy / SMS Energy Services Ltd. It is recorded as operational since January 2023. The determining authority is Barnsley, reference 2017/0117.…

Operational Β· Since 2023
Project stageOperating
  1. PlanningJan 2017 (completed)
  2. ConsentedAug 2017 (completed)
  3. Construction (completed)
  4. OperatingJan 2023 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2026-03-06.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

40.000 MW
Power Capacity
2023
Commissioned

πŸ“‹ Project Overview

Barnsley Battery Energy Storage is a 40 MW battery storage project in Yorkshire and Humber. The applicant or operator on record is G2 Energy / SMS Energy Services Ltd. It is recorded as operational since January 2023. The determining authority is Barnsley, reference 2017/0117.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)40.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperG2 Energy / SMS Energy Services Ltd
Owner / operatorG2 Energy / SMS Energy Services Ltd
Year consented2017
Commissioned / target2023
LocationLand West of Hopewell Street, Stairfoot, Barnsley, South Yorkshire, S70 3ET
RegionYorkshire and Humber
Coordinates53.54867Β°N, 1.4485883Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2017-01-26
2017-08-02
2023-01-01