πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Solar Farm

Barnfield Solar Park

Former Landfill Site Galton Way Kendrick Industrial Estate Swindon, Wiltshire, SN2 2YW

Barnfield Solar Park is a 2.5 MW solar farm project in South West. The applicant or operator on record is Public Power Solutions. It is recorded as operational since December 2018. The determining authority is Swindon.…

Operational Β· Since 2018
Project stageOperating
  1. PlanningAug 2016 (completed)
  2. ConsentedOct 2016 (completed)
  3. ConstructionFeb 2017 (completed)
  4. OperatingDec 2018 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2019-01-02.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2.500 MW
Registered Capacity
2018
Commissioned

πŸ“‹ Project Overview

Barnfield Solar Park is a 2.5 MW solar farm project in South West. The applicant or operator on record is Public Power Solutions. It is recorded as operational since December 2018. The determining authority is Swindon.

Site Schematic

SUBSTATION ? ha Β· 2.5 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)2.500 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperPublic Power Solutions
Owner / operatorPublic Power Solutions
Year consented2016
Construction started2017
Commissioned / target2018
LocationFormer Landfill Site Galton Way Kendrick Industrial Estate Swindon, Wiltshire, SN2 2YW
RegionSouth West
Coordinates51.5737906Β°N, 1.8136095Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround

πŸ“… Project Timeline

2016-08-26
2016-10-25
2017-02-07
2018-12-10