Barnby Manor is a 0.2 MW solar farm project in East Midlands. The applicant or operator on record is Private Developer. The planning permission has expired. The determining authority is Newark and Sherwood, reference 18/02319/FUL.β¦
Expired
Project stageConsent lapsed
PlanningMar 2019 (completed)
ConsentedOct 2019 (completed)
Consent lapsed (project stopped here)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Planning Permission Expired.
Official register: July 2026
Recorded status: Planning Permission Expired. Source record updated 2019-06-04.
Registered planning capacity; not measured generation.
Barnby Manor is a 0.2 MW solar farm project in East Midlands. The applicant or operator on record is Private Developer. The planning permission has expired. The determining authority is Newark and Sherwood, reference 18/02319/FUL.