Onshore Wind

Barmoor

NE of Ford, Northumberland

Barmoor is a 27 MW onshore wind project in North East. The applicant or operator on record is Force 9 Energy/Catamount. The scheme is currently in the planning system, submitted March 2006. The determining authority is Northumberland, reference 06/B/0148.…

Revised
Project stageSuperseded by a new application
  1. PlanningMar 2006 (completed)
  2. Superseded by a new application (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Revised.

Official register: July 2026

Recorded status: Revised. Source record updated 2009-06-10.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

27.000 MW
Registered Capacity

πŸ“‹ Project Overview

Barmoor is a 27 MW onshore wind project in North East. The applicant or operator on record is Force 9 Energy/Catamount. The scheme is currently in the planning system, submitted March 2006. The determining authority is Northumberland, reference 06/B/0148.

Site Schematic

NORTH EAST Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)27.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperForce 9 Energy/Catamount
Owner / operatorForce 9 Energy/Catamount
LocationNE of Ford, Northumberland
RegionNorth East
Coordinates55.6355566Β°N, 2.0333304Β°W

Additional published register fields

Registered technologyWind Onshore
No. of Turbines9
Are they re-applying (New REPD Ref)4163

πŸ“… Project Timeline

2006-03-02