South of Banner Hill Farm, Banner Hill, and Rouncil Lane, Warwickshire, CV8 1NN
Banner Hill Farm, Banner Hill & Rouncil Lane - Battery Storage is a 49.9 MW battery storage project in West Midlands. The applicant or operator on record is Flexion Energy Storage UK Limited. The planning application was refused. The determining authority is Warwick, reference W/β¦
Refused
Project stageRefused
PlanningAug 2022 (completed)
Refused (project stopped here)
Consented (not reached)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Planning Permission Refused.
Official register: July 2026
Recorded status: Planning Permission Refused. Source record updated 2022-10-04.
Registered planning capacity; not measured generation.
Banner Hill Farm, Banner Hill & Rouncil Lane - Battery Storage is a 49.9 MW battery storage project in West Midlands. The applicant or operator on record is Flexion Energy Storage UK Limited. The planning application was refused. The determining authority is Warwick, reference W/22/0941.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
49.900 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Flexion Energy Storage UK Limited
Owner / operator
Flexion Energy Storage UK Limited
Location