E/O Balsillie Avenue, The S/O The Limekilns, Glenrothes, Fife, KY12 7DR
Balsillie Avenue - Roaring Hill Energy Storage Facility is a 19.9 MW battery storage project in Scotland. The applicant or operator on record is Tag Energy UK. It is recorded as under construction since September 2022. The determining authority is Fife, reference 21/01438/FULL.β¦
Under Construction
Project stageUnder construction
PlanningMay 2021 (completed)
ConsentedSep 2021 (completed)
ConstructionSep 2022 (current stage)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Under Construction.
Official register: July 2026
Recorded status: Under Construction. Source record updated 2022-09-15.
Registered planning capacity; not measured generation.
Balsillie Avenue - Roaring Hill Energy Storage Facility is a 19.9 MW battery storage project in Scotland. The applicant or operator on record is Tag Energy UK. It is recorded as under construction since September 2022. The determining authority is Fife, reference 21/01438/FULL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
19.900 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Tag Energy UK
Owner / operator
Tag Energy UK
Year consented
2021
Construction started
2022
Location
E/O Balsillie Avenue, The S/O The Limekilns, Glenrothes, Fife, KY12 7DR