Lands immediately north east o, Moneybroom Road, the junction of Ballinderry Rd, Lisburn, Co. Antrim, BT28 2QP
Ballinderry Road Solar Phase 2 (Lisburn) is a 7 MW solar farm project in Northern Ireland. The applicant or operator on record is RAD Energy One/ Island Green Power. It is recorded as operational since February 2017. The determining authority is Lisburn and Castlereagh, referenceβ¦
OperationalΒ· Since 2017
Project stageOperating
PlanningMay 2015 (completed)
ConsentedOct 2015 (completed)
ConstructionJul 2016 (completed)
OperatingFeb 2017 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2017-04-18.
Registered planning capacity; not measured generation.
Ballinderry Road Solar Phase 2 (Lisburn) is a 7 MW solar farm project in Northern Ireland. The applicant or operator on record is RAD Energy One/ Island Green Power. It is recorded as operational since February 2017. The determining authority is Lisburn and Castlereagh, reference LA05/2015/0157/F.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
7.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
RAD Energy One/ Island Green Power
Owner / operator
RAD Energy One/ Island Green Power
Year consented
2015
Construction started
2016
Commissioned / target
2017
Location
Lands immediately north east o, Moneybroom Road, the junction of Ballinderry Rd, Lisburn, Co. Antrim, BT28 2QP