Avonmouth Resource Recovery Centre (formerly Severn Road)

Former Sevalco Site (North), Severn Road, Avonmouth, Bristol, Avon, BS11 0YU

Avonmouth Resource Recovery Centre (formerly Severn Road) is a 34 MW bioenergy / waste project in South West. The applicant or operator on record is Viridor. It is recorded as operational since December 2020. The determining authority is Bristol, City of, reference 09/04470/F.…

Operational Β· Since 2020
Project stageOperating
  1. PlanningNov 2009 (completed)
  2. ConsentedApr 2011 (completed)
  3. ConstructionApr 2017 (completed)
  4. OperatingDec 2020 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2021-01-12.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

34.000 MW
Registered Capacity
2020
Commissioned

πŸ“‹ Project Overview

Avonmouth Resource Recovery Centre (formerly Severn Road) is a 34 MW bioenergy / waste project in South West. The applicant or operator on record is Viridor. It is recorded as operational since December 2020. The determining authority is Bristol, City of, reference 09/04470/F.

πŸ”§ Technical Specifications

Capacity (MW)34.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperViridor
Owner / operatorViridor
Year consented2011
Construction started2017
Commissioned / target2020
LocationFormer Sevalco Site (North), Severn Road, Avonmouth, Bristol, Avon, BS11 0YU
RegionSouth West
Coordinates51.5293066Β°N, 2.6666673Β°W

Additional published register fields

Registered technologyEfW Incineration

πŸ“… Project Timeline

2009-11-05
2011-04-06
2017-04-15