πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Bioenergy / Waste

Avondale

Shanks Landfill Site, Meikle, Drumgray Road, Greengairs, Airdrie,, Strathclyde

Avondale is a 4 MW bioenergy / waste project in Scotland. The applicant or operator on record is Shanks Avondale. It is recorded as operational since January 2006. The determining authority is North Lanarkshire, reference 01/01447/FUL.…

Operational Β· Since 2006
Project stageOperating
  1. PlanningNov 2001 (completed)
  2. ConsentedJan 2002 (completed)
  3. Construction (completed)
  4. OperatingJan 2006 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2009-10-02.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

4.000 MW
Registered Capacity
2006
Commissioned

πŸ“‹ Project Overview

Avondale is a 4 MW bioenergy / waste project in Scotland. The applicant or operator on record is Shanks Avondale. It is recorded as operational since January 2006. The determining authority is North Lanarkshire, reference 01/01447/FUL.

πŸ”§ Technical Specifications

Capacity (MW)4.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperShanks Avondale
Owner / operatorShanks Avondale
Year consented2002
Commissioned / target2006
LocationShanks Landfill Site, Meikle, Drumgray Road, Greengairs, Airdrie,, Strathclyde
RegionScotland
Coordinates55.9050228Β°N, 3.9450123Β°W

Additional published register fields

Registered technologyLandfill Gas

πŸ“… Project Timeline

2001-11-05
2002-01-29
2006-01-01