Aven Industrial Estate is a 20 MW battery storage project in Yorkshire and Humber. The applicant or operator on record is Max Design Consultancy. The planning permission has expired. The determining authority is Rotherham, reference RB2017/0910.…

Expired
Project stageConsent lapsed
  1. PlanningJun 2017 (completed)
  2. ConsentedJun 2018 (completed)
  3. Consent lapsed (project stopped here)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Planning Permission Expired.

Official register: July 2026

Recorded status: Planning Permission Expired. Source record updated 2020-06-04.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

20.000 MW
Power Capacity

πŸ“‹ Project Overview

Aven Industrial Estate is a 20 MW battery storage project in Yorkshire and Humber. The applicant or operator on record is Max Design Consultancy. The planning permission has expired. The determining authority is Rotherham, reference RB2017/0910.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)20.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperMax Design Consultancy
Owner / operatorMax Design Consultancy
Year consented2018
LocationAven Industrial Estate, Tickhill Road, Maltby, South Yorkshire, S66 7QR
RegionYorkshire and Humber
Coordinates53.4228742Β°N, 1.1649037Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2017-06-16
2018-06-19