Auchencarroch Landfill is a 2.1 MW bioenergy / waste project in Scotland. The applicant or operator on record is Auchencarroch Energy Ltd / CLP. It is recorded as operational since August 2002. The determining authority is West Dunbartonshire, reference WT00239.…

Operational Β· Since 2002
Project stageOperating
  1. PlanningNov 2000 (completed)
  2. ConsentedMay 2001 (completed)
  3. Construction (completed)
  4. OperatingAug 2002 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2009-04-22.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2.100 MW
Registered Capacity
2002
Commissioned

πŸ“‹ Project Overview

Auchencarroch Landfill is a 2.1 MW bioenergy / waste project in Scotland. The applicant or operator on record is Auchencarroch Energy Ltd / CLP. It is recorded as operational since August 2002. The determining authority is West Dunbartonshire, reference WT00239.

πŸ”§ Technical Specifications

Capacity (MW)2.100 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperAuchencarroch Energy Ltd / CLP
Owner / operatorAuchencarroch Energy Ltd / CLP
Year consented2001
Commissioned / target2002
LocationAuchencarroch landfill site, Auchencarroch Road, Jamestown, Alexandria, West Dunbartonshire, Strathclyde
RegionScotland
Coordinates55.9967825Β°N, 4.5333567Β°W

Additional published register fields

Registered technologyLandfill Gas

πŸ“… Project Timeline

2000-11-20
2001-05-10
2002-08-15