Astra Centre, Royal Barn Road - Energy Storage

R/o Astra Centre, Royal Barn Road, Rochdale, Lancashire, OL11 3DT

Astra Centre, Royal Barn Road - Energy Storage is a 40 MW battery storage project in North West. The applicant or operator on record is Arlington Energy Limited. It is recorded as under construction since February 2024. The determining authority is Rochdale, reference 21/01098/FU…

Under Construction
Project stageUnder construction
  1. PlanningSep 2021 (completed)
  2. ConsentedNov 2021 (completed)
  3. ConstructionFeb 2024 (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Under Construction.

Official register: July 2026

Recorded status: Under Construction. Source record updated 2024-02-29.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

40.000 MW
Power Capacity

πŸ“‹ Project Overview

Astra Centre, Royal Barn Road - Energy Storage is a 40 MW battery storage project in North West. The applicant or operator on record is Arlington Energy Limited. It is recorded as under construction since February 2024. The determining authority is Rochdale, reference 21/01098/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)40.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperArlington Energy Limited
Owner / operatorArlington Energy Limited
Year consented2021
Construction started2024
LocationR/o Astra Centre, Royal Barn Road, Rochdale, Lancashire, OL11 3DT
RegionNorth West
Coordinates53.5966167Β°N, 2.178949Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2021-09-02
2021-11-01
2024-02-27