Asda Brackmills Distribution Depot is a 2 MW onshore wind project in East Midlands. The applicant or operator on record is Asda. The planning application was refused. The determining authority is West Northamptonshire, reference 07/0356/FULWNN.…

Refused
Project stageRefused
  1. PlanningDec 2007 (completed)
  2. Refused (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Planning Permission Refused.

Official register: July 2026

Recorded status: Planning Permission Refused. Source record updated 2014-12-19.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2.000 MW
Registered Capacity

πŸ“‹ Project Overview

Asda Brackmills Distribution Depot is a 2 MW onshore wind project in East Midlands. The applicant or operator on record is Asda. The planning application was refused. The determining authority is West Northamptonshire, reference 07/0356/FULWNN.

Site Schematic

EAST MIDLANDS Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)2.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperAsda
Owner / operatorAsda
LocationAsda Distribution Site, Gowerton Road, Brackmills Industrial Estate, Northampton, Northamptonshire, NN4 7BW, Northamptonshire
RegionEast Midlands
Coordinates52.2111916Β°N, 0.8591326Β°W

Additional published register fields

Registered technologyWind Onshore
Turbine Capacity (MW)2
No. of Turbines1

πŸ“… Project Timeline

2007-12-07