Land To East Of Crudie Acre Co, Arbroath, Tayside, Angus, DD11 3ET
Arbroath Battery Storage is a 35 MW battery storage project in Scotland. The applicant or operator on record is Coronation Power / Persimmon Homes. It is recorded as operational since April 2024. The determining authority is Angus, reference 18/00810/FULL.β¦
OperationalΒ· Since 2024
Project stageOperating
PlanningOct 2018 (completed)
ConsentedAug 2019 (completed)
Construction (completed)
OperatingApr 2024 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2026-03-06.
Registered planning capacity; not measured generation.
Arbroath Battery Storage is a 35 MW battery storage project in Scotland. The applicant or operator on record is Coronation Power / Persimmon Homes. It is recorded as operational since April 2024. The determining authority is Angus, reference 18/00810/FULL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
35.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Coronation Power / Persimmon Homes
Owner / operator
Coronation Power / Persimmon Homes
Year consented
2019
Commissioned / target
2024
Location
Land To East Of Crudie Acre Co, Arbroath, Tayside, Angus, DD11 3ET